Eskom MYPD6 · 30 January 2025 decision and the R54.7 billion RAB redetermination
Where it stands: Redetermined MYPD6 revenues are in tariffs from 1 April 2026 for Eskom customers and 1 July 2026 for municipalities
NERSA decided Eskom's sixth multi-year price determination on 30 January 2025 for 2025/26 to 2027/28, cutting the application heavily. Eskom took the decision on review, a settlement was interdicted, and on 21 December 2025 the High Court set the decision aside and remitted it. The redetermination approved on 7 February 2026 gives Eskom R54 734 million more, phased so that the 2026/27 increase becomes 8.76% and 2027/28 becomes 8.83%.
The problem
Eskom's allowable revenue is set under a cost-of-service, rate-of-return methodology (MYPD4, published October 2016) that values a 40 GW coal fleet at depreciated replacement cost. Small changes in the regulatory asset base move tariffs by whole percentage points, and the parties have litigated the RAB repeatedly, including a 2022 court order on valuation. Eskom applied for revenues built on an average Generation RAB of R828 717 million in 2025/26 rising to R909 656 million in 2026/27; NERSA cut it, Eskom sued, and the resulting legal uncertainty sat directly on the tariff paid by every South African customer and on the cost base of every energy-intensive exporter.
What it does
At its meeting on 30 January 2025 the Energy Regulator approved Generation allowable revenue of R249 682 million for 2025/26, R258 574 million for 2026/27 and R257 734 million for 2027/28 (including approved RCA liquidation), against an application of R291 640 million, R323 952 million and R322 376 million, and set separate determinations for Distribution and for NTCSA. Reasons for Decision were published on 9 June 2025. Eskom filed a review on 26 June 2025 attacking the depreciated replacement cost, transfers to commercial operation, work under construction, component-level depreciation and RAB roll-forward, and proposed a settlement of R62 676 million; the Electricity Subcommittee recommended R54 billion and the Regulator settled on 30 July 2025. AfriForum and the Minerals Council interdicted the settlement in October 2025, and on 21 December 2025 the High Court reviewed and set aside the decision and remitted it for a procedurally fair redetermination. NERSA consulted (comments closed 21 January 2026) and, on 7 February 2026, approved revised Generation RAB-related revenues of R188 005 million (R70 678 million returns plus R117 327 million depreciation) against the R216 416 million applied for, cutting the WACC from 5% to 4.08% in 2026/27 and from 6% to 4.2% in 2027/28.
Market effect
The redetermination hands Eskom R54 734 million of additional revenue, all of it depreciation and none of it extra return, and NERSA chose phased recovery (Option 2): R12 000 million in 2026/27 and R23 013 million in 2027/28, with R19 721 million deferred beyond MYPD6. That converts the original headline path of 12.74%, 5.36% and 6.19% into 12.74%, 8.76% and 8.83%. Full recovery (Option 1) would have produced 12.21% and 7.39% with a sharper first-year shock; NERSA's own economic impact assessment put Option 1 at about 41 104 jobs lost in 2026/27 against 22 790 under Option 2, and GDP losses of R12 710 million versus R7 047 million. For an industrial buyer this is a roughly 8.8% nominal tariff step on 1 April 2026 for Eskom-supplied customers and 1 July 2026 for municipal customers, on top of a 12.74% step the year before. It sharpens the arithmetic behind wheeled private PPAs, rooftop PV and captive generation, and it is the single largest driver of the carbon-intensive industrial cost base outside coal and logistics.
Key numbers
- Additional revenue from the redetermination
- R54 734 million (R0 additional returns, R54 734 million additional depreciation)
- Resulting price path
- 8.76% in 2026/27 and 8.83% in 2027/28 under phased recovery, against 5.36% and 6.19% before the redetermination
- Generation allowable revenue approved 30 January 2025
- R249 682m (2025/26), R258 574m (2026/27), R257 734m (2027/28)
- WACC applied in the redetermination
- 4.08% in 2026/27 and 4.2% in 2027/28, cut from 5% and 6%
- Deferred balance
- R19 721 million recovered beyond the MYPD6 control period
Who gains and who pays
- Eskom Holdings (gains): R54.7 billion additional allowable revenue; interest cover projected at 5.68x in 2026/27 and debt service cover at 1.46x.
- Energy-intensive industry and mining (costs): Two consecutive double-digit or near-double-digit increases; the Minerals Council litigated the settlement.
- Municipal distributors and their customers (costs): Bulk purchase cost rises from 1 July 2026 and is passed into separately approved municipal tariffs.
- Private IPPs, wheeling traders and rooftop PV installers (gains): Every tariff step widens the spread against a private PPA or self-generation.
- NERSA (obligation): Must run lawful, rational and transparent processes under PAJA after two adverse High Court outcomes.
Implementation
Eskom had to submit NERSA-approved tariffs to Parliament by 15 March 2026 for implementation on 1 April 2026; municipal tariffs follow on 1 July 2026 after separate NERSA approval of each municipality's schedule. The Reasons for Decision on the redetermination were published on 12 July 2026, with an annexure analysing stakeholder comments and an economic impact report. Regulatory Clearing Account applications continue to reopen closed years: NERSA decided the 2022/23 RCA (year 1 of MYPD5) on 9 May 2025, and the 2025/26 Eskom Retail Tariff and Structural Adjustment decision was issued the same day. The unresolved items are the treatment of the deferred R19 721 million after 2027/28, the next RCA liquidations, and whether AfriForum, the Minerals Council or Eskom return to court over the redetermination.
Concerns
- The deferred R19.7 billion is an unfunded liability that lands in MYPD7 or a later RCA
- Two successive High Court setbacks make every NERSA revenue decision reviewable and therefore provisional
- Depreciated replacement cost valuation of ageing coal plant keeps the RAB, and the tariff, contestable
- Tariff increases above inflation accelerate grid defection, shrinking the sales base that has to carry the same fixed costs
- NERSA's own modelling projects 22 790 job losses in 2026/27 from the chosen option
- Municipal arrear debt to Eskom is not addressed by the revenue determination
Dates to watch
- 1 April 2027: Third MYPD6 year takes effect at 8.83% for Eskom-supplied customers
- 1 July 2027: Municipal tariff implementation of the same determination
- 2028: MYPD6 control period ends; MYPD7 application and the deferred R19.7 billion fall due
Sources
- Decision and Reasons for Decision: Eskom MYPD6 Generation RAB Re-determination (7 February 2026 decision, published 12 July 2026), National Energy Regulator of South Africa (official text)
- Reasons for Decision: Eskom MYPD6 revenue application, Generation business, 2025/26 to 2027/28, National Energy Regulator of South Africa
- Reasons for Decision: Eskom MYPD6 revenue application, NTCSA (transmission), National Energy Regulator of South Africa
- NERSA electricity regulator decisions index (MYPD6, RCA, ERTSA), National Energy Regulator of South Africa
Checked against sources on .