Binding planning · the Plan de Desarrollo del Sector Eléctrico each May and the CFE-led generation and transmission build to 2030
Where it stands: Binding-planning framework in force since the reglamento of 3 October 2025; annual plan cycle and state-share calculation being operationalised
The 2025 framework replaced indicative PRODESEN planning with binding planning: SENER must publish a Plan de Desarrollo del Sector Eléctrico each May, though the first one came in October 2025, calculates the state's share of injected generation each February, and every permit, interconnection and mixed-investment project must conform to the plan, which is the instrument carrying the CFE-led generation and transmission expansion to 2030.
The problem
Between 2019 and 2024 Mexico added far less generation than demand growth required while nearshoring pushed industrial load up sharply in the Bajío and the north; reserve margins in the northwest and the peninsula fell below adequacy criteria, and CENACE repeatedly declared operating-state alerts. Transmission investment had been almost frozen since 2018, so the constraint was as much network as capacity: renewable-rich zones in Oaxaca, Sonora and Baja California could not export to load centres. The 2014 framework relied on private investment responding to market signals and to the PRODESEN as an indicative document, and after 2021 those signals no longer produced investment. The new constitutional order therefore required a planning instrument that actually binds.
What it does
The Ley del Sector Eléctrico and its reglamento of 3 October 2025 make planning vinculante and place it at the centre of the permitting system. Article 7 of the reglamento provides that sector planning is developed in the Plan de Desarrollo del Sector Eléctrico, which article 12 requires SENER to publish in May of each year, with the underlying programmes posted on the SENER, state company and CENACE portals and, where applicable, in the DOF within ten working days of authorisation. Article 9 requires SENER, by the last working day of February each year, to calculate the state's participation in generation under a methodology it issues, as state-injected generation divided by total injected generation times one hundred, and for forward-looking assessments to use estimated total injected generation built from national demand scenarios and estimated state generation that takes account of generation and transmission expansion plans, project progress and an adjustment factor for execution and commissioning-delay risk. On the basis of that result SENER must identify the additional generation, transmission and other electrical infrastructure the state needs to develop, include it in the plan and take the steps to execute it. Article 13 lets SENER designate Strategic Projects that receive administrative simplification and expedited processing. Both state and private projects, including the long-term production and mixed-investment schemes of the statute, are subject to the binding planning criteria, permits and authorisations are granted against compliance with the planning provisions SENER issues, and interested parties have twenty working days from publication of the plan to act on the opportunities it identifies.
Market effect
Binding planning reverses the direction of information in the Mexican market. Under the 2014 design a developer chose a site, requested an interconnection study and let CENACE's queue and the nodal price decide; under the 2025 design the state decides what is needed and where, publishes it on the statutory annual cycle, and the private route in is either a long-term production contract for a project the plan identifies or a mixed-investment vehicle in which CFE holds at least 54 percent. That makes the May publication and the February share calculation the two dates on which the entire Mexican pipeline turns, and it makes CFE's own capital programme the determinant of how much private capacity can be permitted at all: if CFE's projects slip, the execution-risk adjustment in article 9 pushes the state's estimated share down and the room for private permits narrows rather than widens. Transmission is where the plan matters most to prices, because congestion between the northwest, the Isthmus and the central load centres is what keeps locational marginal prices dispersed and renewable output curtailed; the strategic-project designation is the mechanism intended to accelerate those lines. For lenders the practical change is that the bankable document is no longer an interconnection study but a place in the plan.
Key numbers
- Statutory publication month, and what actually happened
- The reglamento has SENER publishing the Plan de Desarrollo del Sector Eléctrico in May each year. The first one did not follow that calendar: it was published in the DOF on 17 October 2025
- Planning horizon
- Fifteen years, 2025 to 2039
- Starting point
- 90,543 MW of installed capacity in 2024, 36.9% of it clean; clean capacity had grown 132.5% since 2010 to reach 33,441 MW
- Existing network
- 56,720 km of 161-400 kV transmission and 54,418 km at 69-138 kV, with 116,625 transformer banks
- Electrification
- 99.73% of the population connected, 468,150 people still not; the 2025 programme covers 4,373 projects for 2,402 million pesos
- State share calculation
- By the last working day of February each year, as state-injected generation divided by total injected generation times 100
- State floor
- At least 54 percent of average injected energy in a calendar year
- Response window
- Twenty working days from publication of the plan for interested parties to act
Who gains and who pays
- Comisión Federal de Electricidad (gains): Its capital programme becomes the backbone of the binding plan and the majority partner in mixed investment.
- Private developers and infrastructure funds (mixed): A clear pipeline if they are in the plan, no route if they are not.
- Industrial load centres in the Bajío and the north (costs): Dependent on planned transmission and capacity being delivered on time.
- CENACE (obligation): Must align interconnection studies, programmes and market operation with the binding plan.
- Renewable-rich states such as Oaxaca, Sonora and Baja California (gains): Planned transmission reinforcements are the condition for exporting their resource.
Implementation
SENER must first issue the methodology behind the February calculation and the disposiciones administrativas de carácter general for binding planning, then publish the plan each May and the associated programmes within ten working days of authorisation; CENACE aligns its programmes and interconnection processes to it, and the CNE grants permits against compliance with it. The state company's investment programme for generation and transmission to 2030, announced alongside the reform package and carried into the plan, is the concrete content of the framework. Because the plan is annual and the state-share calculation precedes it by three months, the sequencing is predictable and worth diarising. Delivery risk sits with CFE's execution capacity and with the financing of transmission, which competes with generation inside the same balance sheet.
Concerns
- CFE's ability to finance and execute both generation and transmission on schedule
- Private capacity rationed by an annual ratio rather than by system need
- Transmission bottlenecks persisting between renewable zones and load centres
- Reduced role for market signals and the interconnection queue in siting decisions
- Transparency and contestability of the strategic-project designation
Dates to watch
- 2027-02: SENER calculation of the state's share of injected generation
- 2027-05: Publication of the next Plan de Desarrollo del Sector Eléctrico
- 2030: Horizon of the current generation and transmission expansion programme
Sources
- Reglamento de la Ley del Sector Eléctrico (DOF 03-10-2025), Título de la Planeación Vinculante, Control y Prevalencia del Estado, Cámara de Diputados del H. Congreso de la Unión (official text)
- ACUERDO por el que la Secretaría de Energía emite el Plan de Desarrollo del Sector Eléctrico, Diario Oficial de la Federación, Secretaría de Energía
- Secretaría de Energía: planeación del sector eléctrico y proyectos estratégicos, Secretaría de Energía
- Comisión Federal de Electricidad, Comisión Federal de Electricidad
- CENACE: programmes and system operation, Centro Nacional de Control de Energía
Checked against sources on .